Capital cost
What actually drives
the capital cost.
There is no credible price per tonne for a pyrolysis plant. What this page gives you instead is the scope structure to build your own comparable numbers.
Get help with your projectWhy no numbers
There is no credible
price per tonne.
The same nominal throughput can differ in installed cost by a multiple depending on feedstock, product specification, the emissions limits at your site, ground conditions, existing utilities, local fabrication costs and where the supplier drew the edge of their scope.
Use this page as a checklist
Take each line below to every quotation you hold and mark it included, excluded or unclear. The pattern usually explains the price difference entirely.
“Unclear” is an answer
Items a supplier will not place firmly inside or outside scope in writing tend to land on the buyer. Resolve them before signature, not during commissioning.
The second number
Capital gets the attention; operating cost decides whether the plant survives. Energy, labour, consumables, maintenance, residue disposal and feedstock price belong in the model from the start.
Why published price-per-tonne figures mislead, and what to do instead
A figure that excludes feed preparation, a figure that assumes an existing building, and a figure that includes full emissions control and commissioning describe three different projects. Comparing them as though they were the same purchase is the most common and most expensive error in this market.
What can be done rigorously is to establish the scope completely, then obtain real quotations against that fixed scope. The resulting numbers are yours, they are current, and they are comparable.
On precision: the engineering profession has formal conventions for how accurate an estimate can be at each stage of project definition. The classification system published by AACE International as a recommended practice is the standard reference, and it is worth asking a supplier which estimate class their figure corresponds to. A “firm price” for a plant that has not been engineered for your site deserves a follow-up question about what exactly has been engineered.
What a budget contains
Ten scope blocks.
Confirm each one.
A complete plant budget divides into the blocks below. Confirm in writing which of them a quotation covers; the boundary, not the headline figure, is what makes two proposals comparable.
Equipment is one block of ten
Feed preparation, abatement, civils, utilities, control and commissioning each carry real cost and are each capable of sitting outside a quotation.
Owner’s costs are never in a quote
Feedstock testing, permitting, consultants, insurance, financing and contingency are yours, and they are not small.
Write the scope first
Fixing the boundary yourself is the single highest-value piece of owner’s work in the project.
Open the full scope-block table
| Scope block | Typically includes | What to confirm in writing |
|---|---|---|
| Feed reception and preparation | Tipping and storage area, screening, size reduction, separation of metals or other unwanted fractions, drying where needed, conveying | The input specification the process equipment assumes, and whether the equipment to get your actual material to that specification is inside the price |
| Main process equipment | The conversion vessel and its heating arrangement, vapour take-off, condensation and separation, solids removal and cooling | Materials of construction, the basis for any guaranteed figure, and which items are wear parts |
| Gas handling and energy recovery | Non-condensable gas collection and cleaning, the burner or engine that uses it, heat recovery | Whether gas use is included or flaring is assumed, and what that assumption does to your permit and energy balance |
| Emissions control and monitoring | Abatement for combustion and process vents, continuous or periodic monitoring, stack arrangements | Which specific limit values the design was sized against, and who carries the risk if the regulator sets tighter ones |
| Product handling and storage | Liquid tankage and transfer, solids packaging or bulk handling, weighing, loading, quality sampling | Whether storage is sized for your logistics, and whether product conditioning needed to meet a buyer’s specification is included |
| Civils, structures and site works | Ground investigation, foundations, drainage, bunding, hardstanding, buildings, roads, fire water provision | Almost always outside an equipment quotation. Confirm explicitly and budget locally |
| Utilities and connections | Electrical supply and distribution, water, compressed air, inert gas, cooling, grid or network connection works | The capacity required, whether the existing site supply is adequate, and the cost and lead time of any connection upgrade |
| Control, safety and integration | Control system, instrumentation, interlocks, functional safety assessment, fire and gas detection | Who is responsible for integrating separately supplied packages into one controlled, safe plant |
| Engineering, installation, commissioning | Detailed engineering, transport and duties, erection, mechanical completion, commissioning, operator training, documentation | Whether supervision only or full installation is offered, and what the performance test actually consists of |
| Development and owner’s costs | Feedstock testing, permitting, consultants, owner’s engineer, insurance, financing costs, contingency | Never in a supplier quotation. These are owner’s costs and they are not small |
Exclusions
Eight items missing from
the first number you see.
These are the items most often outside an equipment quotation. Their absence is usually legitimate — a supplier has no way to price your ground conditions — but they are still your project and your budget.
Everything below ground
Ground investigation, piling, foundations and drainage are site-specific, routinely excluded, and capable of surprising a project badly.
Getting feed to specification
Shredding, screening and drying to reach the assumed input specification is part of your project whether or not it is in the quotation.
Contingency
A first-of-a-kind or first-for-this-feedstock installation without contingency is an aspiration rather than a budget.
See all eight, with what each one covers
- Everything below ground. Ground investigation, piling, foundations and drainage are site-specific and routinely outside an equipment scope.
- Getting the feed to specification. If the process assumes material at a given size and moisture, the equipment needed to achieve that is part of your project.
- Final abatement and monitoring. Sized against the limits that apply to your permit, not a generic allowance. A jurisdictional question before it is an equipment question.
- Product conditioning to a saleable grade. Filtration, de-watering, milling, pelletising or upgrading to meet a buyer’s specification is often a separate plant and a separate price.
- Spares and first fills. Commissioning spares, a holding of critical parts, catalyst or media first fills, lubricants and inert gas all have to be bought before the plant runs.
- Freight, duties and local compliance. Shipping, insurance, import duty, and modification to satisfy local electrical, pressure and machinery regulations. The last can be substantial on imported plant.
- Owner’s costs. Your own engineering oversight, legal work, permitting, feedstock trials, insurance during construction and financing costs.
- Contingency. Size it against how much of the plant is genuinely proven on your material.
Method
Stop comparing documents.
Compare projects.
Write the scope yourself, once, and require every supplier to price against it. Then normalise the quotations onto a single sheet and fill the gaps with your own estimates.
Require line items
A single lump sum cannot be compared or negotiated intelligently. Ask for the breakdown to follow your scope blocks.
Normalise onto one sheet
Scope blocks down the rows, suppliers across the columns. The totals frequently reverse the ranking of the quoted figures — that reversal is the value of the exercise.
Price the risk too
Liquidated damages, retention, bonds and staged payment against demonstrated milestones are what convert a claim into something enforceable.
The five steps, and the minimum rows for your sheet
1. Write the scope before you ask for a price
Define the feedstock with a laboratory analysis and a stated range, not a category name. Define the product specification each stream must meet. State the site conditions and available utilities, state the emissions limits that apply, and state explicitly what you expect the supplier to provide and what you will provide yourself.
2. Require a priced line-item breakdown
Ask for the breakdown to follow your scope blocks. Where a supplier prefers to quote a lump sum, you are being asked to accept the boundary they chose rather than the one your project needs; it is reasonable to ask for structure before you compare.
3. Normalise every quotation onto one sheet
Put your scope blocks down the rows and the suppliers across the columns. Fill the gaps with your own estimates so that every column describes the same complete project.
4. Add the operating model
Capital cost chosen without operating cost is a false economy that repeats annually. Energy consumption, labour, maintenance, consumables, residue disposal and the delivered price of feedstock decide whether the plant is viable. A somewhat more expensive plant with lower energy demand and longer intervals between interventions can be the cheaper asset within a few years.
5. Price the risk, not just the equipment
Ask what happens if the plant does not reach the guaranteed figures. Liquidated damages, retention, performance bonds and staged payment against demonstrated milestones are the mechanisms that make a figure enforceable. Their presence or absence tells you how the supplier themselves views the risk.
Comparison sheet: minimum rows
- Feed reception and preparation
- Main process equipment
- Gas handling and energy recovery
- Emissions control and monitoring
- Product handling and storage
- Civils, structures, site works
- Utilities and connections
- Control, safety and integration
- Engineering, installation and commissioning
- Freight, duties and local compliance
- Spares, first fills and training
- Owner’s costs and contingency
Where to check the requirements at source
- AACE International — Recommended practices, including cost estimate classification
- US EPA: Title V operating permits — How major stationary sources are permitted in the United States
- US EPA: New Source Review — Pre-construction permitting for new and modified sources
- European Commission: waste and recycling — How input material and residues are classified in the EU
Offered as further reading. None of these bodies is cited in support of a figure on this site, and none endorses it.